If 4 electricians can wire some new houses in 20 days, how many electricians would be required to do the job in 10 days?
a. 30
b. 8
c. 45
d. 2

Respuesta :

frozenpods
frozenpods frozenpods
  • 13-02-2022

Answer:

2

Step-by-step explanation:

20/2 = 10

4/2 = 2

Answer Link

Otras preguntas

The first tax cut designed to stimulate the economy and promote full employment was enacted by president ________. a. theodore roosevelt b. lyndon b. johnso
An Elizabethan theater is almost identical to a modern-day American theater.
which unit of measure would be appropriate for the area of a soccer field that is 105 meters long and 67 meters wide
Samatha ran 3.5 miles on saturday. on wednesday ,she ran 5.2 miles. what was her percent increase to the nearest percent?
PLEASE HELP ME FOR EXTRA POINTS AND BRAINLIEST ANWSER
find the area of a regular hexagon with apothem 3sqrt3. Will mark as branliest
If a rectangular swimming pool has a volume of 16,500 cubic feet, a depth of 10 feet, and a length of 75 feet, what is the width of the pool, in feet?A. 22B. 26
what is the correct answer
I need help plz !!!!!!!
Actin and myosin are important proteins associated with the Select one: a. contraction of muscles. b. synthesis of glycogen. c. production of hemoglobin. d. pol