is A and B can do a piece of work in 6 and 12day respectively how m
any part of work can they do in 4 day​

Respuesta :

wolf1728
wolf1728 wolf1728
  • 12-08-2021

Answer:

6 * 12 / (6+12) = 72 / 18

If they work together they can finish in 4 days.

Source: http://www.1728.org/work.htm

Step-by-step explanation:

Answer Link

Otras preguntas

Do you think that parents should be able to design their babies using gene technology such as CRISPR? Make sure you have 4 or 5 sentences for your answer.
Out of 20 friends, 4/5 are going to the party. How many friends are going to the party?
Can someone please help me? :(
Please helpp!! !!!!!!!!!!!!!!!:)
When managers use suppliers and manufacturers outside of the organization to provide goods or services the company previously supplied itself, it is called
Which shows the classification of a human? Animalia, Arthropoda, Insecta, Lepidoptera, Nymphalidae, Morpho, Morpho Peleides Animalia, Chordata, Amphibia, Anura,
find the area for the shaded region
What is the median of the data represented by the box plot?A number line ranging from 0 to 143.75 with a box encompassing the numbers 12.5, 20, and 65.Enter you
The first description of the narrator and the friends who change my life what does the author‘s word choice reveal about the narrator
How to say "The last time I visited someone was a week ago. My friend came to my house for lunch. We talked and ate." in spanish