The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF).
a. True
b. False

Respuesta :

Limosa
Limosa Limosa
  • 15-01-2020

Answer:

Option B i.e., False is the correct option.

Explanation:

The following statement is incorrect because, It is the logical relationship not the logical dependency to recognize the series of the activity of the project details. So, that's why the following option is correct according to the given statement. the following relationship is also established between the specific schedule.

Answer Link

Otras preguntas

Which religion did the Gupta Dynasty favor? Buddhism Christianity Hinduism Judaism
A nurse is caring for a patient administered ethotoin. what are signs of toxicity for which the nurse should monitor the patient?
eric kweeder can paint a wall in 20 mins. His brother Jessup can paint the same wall in 30 mins. How long will it take them working together?
A diver swims in a pool that is 30 m deep. the diver swims 20 m above the bottom. if the diver descends to 10 m above the bottom, what is the absolute pressure?
how did capitalist policies differ from mercantilist policies in 18th 19th century europe
Evaluate 15/r - 1 when r = 5
The staphylococcus infection of the skin that causes pink, water-filled, raised lesions is known as ________.
During the nineteenth century, the term floaters referred to
With asymmetric encryption, two different keys are used for encoding and decoding a message. a. True b. False
Calling all chemists...please help me!  Ive attached a screen shot of the problem