Using the PERT estimate, calculate the estimated duration of an activity given:
Optimistic Estimate = 21 days
Pessimistic Estimate = 110 days
Most Likely Estimate = 55 days
a) 62.5 days
b) 74 days
c) 65 days
d) 68.5 days

Respuesta :

Otras preguntas

How did Roosevelt often talk directly to the American people? a.film news reels b. radio fireside chats c. large public speeches d. newspaper editorials
what are facts about a cylinder
In the book hatchet chapter 8. Brian discovered what he believed to be the most important rule of survival explain it.
The mass of an electron is approximately 9 × 10-28 grams, while the mass of a neutron is approximately 2 × 10-24 grams. Which of the following is true? The mass
When you display food in ice, the food must?
-2 - 4n -5n≤-11 how do you solve this?
Poetry and short stories are examples of creative writing. true or false.
What body of water did the colonist cross to come to North America
Find the rational roots of x4 + 8x3 + 7x2 – 40x – 60 = 0 (1 point)2, 6. –6, –2. –2, 6. –6, 2.
If 5 is added to a number and the result is doubled, 16 is obtained what is the number